Planned Features
Fellowfield is being developed with the following phases and estimated timeline:
PHASE 1
Winter/Spring 2022
Township Approval of Park Plan
Initial Wildlife and Vegetation Surveys
Fundraising Begins

PHASE 3
Winter/Spring 2023
Construction of Discovery Stations
Habitat Restoration Part 2
Education Workshop Planning Committees

PHASE 2
Summer/Fall 2022
Construction of
Park Entrance, Trails, & Bridges
Habitat Restoration Part 1
Discovery Station Planning Committees

PHASE 4
Summer/Fall 2023
Construction of Welcome Center
1st Annual Environmental Mystery Event
Design of Education Workshops

Official opening and full education programming: SPRING 2024